Project 1 – ARU

Project #1 - ARU
April 25, 2024 (Thursday)

Assembling braces and forms for cantilever beam and adding braces on form of beams

April 26, 2024 (Friday)

Assembling braces and forms for cantilever beam, adding braces on forms of beams, 2 labors help clearing on land property and continue dismantling braces and frameworks of slab 2nd span ground floor

April 27, 2024 (Saturday)

Continue dismantling braces and frameworks of slab 2nd span ground floor and assembling braces and forms for cantilever beam

April 29, 2024 (Monday)

Tying stirrups on cantilever beam, assemble additional braces for slab and labors continue dismantling braces/forms on slab ground floor

April 30, 2024 (Tuesday)

Continue assembling additional braces for slab, assembling forms of slab, labors hauling sands and gravels

May 1, 2024 ( Wednesday)

Continue assembling additional braces for slab, assembling forms of slab and labors hauling sands, gravels

May 02, 2024 (Thursday) - ARU

Continue assembliing forms of slab, laying rebars of slab and adding extra braces on forms

May 03, 2024 (Friday) - ARU

Continue laying rebars of slab and adding extra braces on forms below

May 04, 2024 (Friday) - ARU

Continue laying rebars of slab, adding extra braces on forms below, labors hauling materials

May 06, 2023 (Monday) - ARU

Installing electrical conduits, continue adding extra braces on forms of slab, labors hauling materials, continue adding extra braces on forms of slab

May 07, 2024 (Tuesday) - ARU

Installing electrical conduits, continue adding extra braces on forms of slab, placing dowel bars on partitions

May 08, 2023 (Wednesday) - ARU

Concreting of slab 2nd floor, done concreting of slab 2nd floor 1st span at 11:20pm

May 09, 2024 (Thursday) - ARU

Clearing ground floor/preparation for building columns, tying lateral ties for column, bagging gravel, sands

May 10, 2024 (Friday) - ARU

Continue tying lateral ties for column, assembling forms for column, some labors hauling sands,gravel

May 11, 2024 (Saturday) - ARU

Concreting of columns, continue assembling forms for column

May 13, 2024 (Monday) - ARU

Dismantling forms of columns, labors continue hauling sands and gravel

May 14, 2024 (Tuesday) - ARU

Clearing/preparing for forms of beam, assembling forms of beam

May 15, 2024 (Wednesday) - ARU

Dismantling forms, continue assembling forms for beams, fabricating stirrups for beam, labors hauling sands,gravel

May 16, 2024 (Thursday) - ARU

Assembling frames and braces for beam, preparing rebars of beam, labor hauling sands and gravel, continue fabricating stirrups

May 17, 2024 (Friday) - ARU

Laying rebars of beam, continue assembling braces for beams

May 18, 2024 (Saturday) - ARU

Continue laying rebars of beam, continue assembling braces for beams

Classichaus services give you the professional manpower services. Started in 2013, Our team do the following services accredited by DOLE PRPA License.

Contact Us

Address: Ortigas Center, Pasig City
Phone: +63 917 653 5836
Email: classichaus@hotmail.com

© Copyright 2023 Classichaus. All Rights Reserved.

Reset password

Enter your email address and we will send you a link to change your password.

Get started with your account

to save your favourite homes and more

Sign up with email

Get started with your account

to save your favourite homes and more

By clicking the «SIGN UP» button you agree to the Terms of Use and Privacy Policy
Powered by Estatik