Innovative Modern Design and Work
classichaus@hotmail.com
Ortigas Center Pasig City
For more photos of our projects, please visit our Facebook page.
Continue laying CHB on 2nd floor, laying rebars of stair on left ground floor and continue electrical wiring.
Continue electrical wiring, plastering of walls on 2nd floor and preparing for flooring slab on unit on ground floor.
Plastering walls on 2nd floor
Plastering on 2nd floor and adding rebars for stair on left ground floor
Continue plastering on 2nd floor, assembling forms for stair on left ground floor and continue assembling roof trusses
Continue plastering on 2nd floor, continue assembling roof trusses, continue electrical wiring and labors preparing materials for concreting of stair
Continue plastering on 2nd floor, continue assembling of roof trusses and concreting of stair on left side ground floor
Continue plastering on 2nd flr., continue installing roof trusses, laying rebars for flooring on Unit 2 ground floor, preparing for laying chb for.partitions on 2nd floor
Continue installing C-purlins, concreting of flooring Unit 2 ground floor, plastering on 2nd flr.
Continue installing C-purlins, plastering on 2nd flr., laying chb for toilet&bathroom
Continue installing C-purlins, laying chb for t&b 2nd flr, preparing for plasteringof wall last panel on ground floor
Continue installing sag rod in purlins
Continue installing purlins on right side, plastering on ground floor, sieving sands for plastering
Continue installing purlins on right side, continue plastering on ground floor
Continue installing purlins on right side, clearing materials on national road, as ordered by municipal and barangay
– continue installing purlins on right side– continue clearing materials on national road, as ordered by municipal and barangay– continue installing electrical conduits– clearing on 2nd floor
– continue installing purlins on right side– continue installing electrical conduits– clearing on 2nd floor
– continue installing purlins on right side– continue installing electrical conduits– clearing on 2nd floor– plastering on ground floor
– continue installing purlins on right side– continue installing electrical conduits– plastering on ground floor
– continue installing purlins on right side– preparing for partition of CR on ground floor– applying primer on purlins– continue plastering on ground floor
– continue installing purlins on right side– laying chb for partition on ground floor– applying primer on purlins– continue plastering on ground floor
Classichaus services give you the professional manpower services. Started in 2013, Our team do the following services accredited by DOLE PRPA License.
Address: Ortigas Center, Pasig CityPhone: +63 917 653 5836Email: classichaus@hotmail.com
to save your favourite homes and more
Don't have an account? Sign up
Enter your email address and we will send you a link to change your password.
Already have an account? Log in
You'll use it to sign in, and we'll use it to contact you.
Enter the destination URL
Or link to existing content